Good afternoon Nick,

 

As requested, please find below outstanding work orders and cost estimates to complete;

 

•    Work Order 11371045 – Fuselage Simulator main isolation valve: $8,234.60

•    Work Order 11320269 – Fuel Spill gas actuator: $13,466.20

•    Work Order 11320235 – Fuselage LPG lines showing corrosion: $18,118.10

•    Work Order 11435883 – PLC Lightning Strike (Invoiced): $8,943.00

•    Work Order 11461251 – Gas line cathodic testing & report: $5,051.20

•    Work Order 11320333 – Gas detector head failure: $6298.25

                                   

                                                              Total Cost inc. GST: $60,111.35

 

If you require any further information, please don’t hesitate to contact myself.

 